If you're comparing homes east of Maryville, between Old Knoxville Highway and Lamar Alexander Parkway, the Tennessee seller disclosure form gives you exactly one question that might touch the Pellissippi Parkway Extension. It doesn't mention highways or right-of-way at all. Meanwhile, on July 16, 2026, Blount County commissioners voted 14-7 to put $5 million toward buying land for the road. TDOT now lists right-of-way as funded in Fiscal Year 2026, with construction expected to start in Fiscal Year 2036.
That ten-year gap between buying the land and building the road is the period buyers need to understand. TDOT's own documents show that homes built inside the planned footprint have already raised the estimated number of affected households. Local officials named that trend as the reason to buy land now instead of later.
The One Line on the Disclosure Form
Tennessee's residential property condition disclosure, the RF201 form most local transactions use, has no question that names condemnation, eminent domain, a planned highway, or proposed right-of-way. The closest it comes is this:
"Any authorized changes in roads, drainage or utilities affecting the property, or contiguous to the property?"
Elsewhere, the form asks about "encroachments, easements, or similar items that may affect your ownership interest" and about "neighborhood noise problems or other nuisances." If a seller knows about an authorized road change affecting the property or land next to it, the roads question could cover it. But the form never asks whether a house sits near a proposed corridor.
The state law behind the form also limits what you can expect. Under Tenn. Code Ann. § 66-5-202, sellers must disclose known material defects, and they aren't required to investigate or inspect anything to complete the disclosure. The form itself says it isn't a warranty and doesn't replace inspections. A seller who has never opened a TDOT plan sheet can answer every question honestly and still never mention the extension.
Why the Count of Affected Homes Nearly Doubled
When the project's environmental review was finalized in 2015 and 2017, TDOT expected 11 residential relocations and one business relocation. TDOT updated the plans and ran a new Conceptual Stage Relocation Plan, dated February 3, 2023. That estimate came out at 21 residential relocations and one business.
The relocation plan breaks it down this way:
| Anticipated relocation type | Count |
|---|---|
| Single-family homes | 17 |
| Mobile homes | 4 |
| Businesses | 1 |
| Multifamily units, nonprofits, farms | 0 |
The important detail is in the notes. Three of the 17 single-family homes weren't on TDOT's plans at all. Two were still under construction, and the third looked recently built. The planners also observed that those three newer homes appeared larger than the other single-family homes in the path.
That's the mechanism behind this summer's vote. In The Daily Times' account of the July meeting, officials said they're buying right-of-way now because property values have climbed and because development could move into the footprint. That would raise the purchase price and increase the number of affected residences. Each new house built inside the corridor costs taxpayers more and adds one more household to the relocation count. Those houses can then sell to buyers who learn about the road only after closing.
The Money Behind the Timeline
The local share is $11 million toward a right-of-way phase estimated at about $75 million, with state and federal funds covering the rest. Alcoa approved $2 million. Maryville authorized a little less than $4 million in May. The county's $5 million comes in four payments of $1.25 million, starting in June 2027.
The vote didn't pass quietly. The crowd overflowed the commission room, and more than 20 speakers spoke against it during public input. Opponents pointed out that the TDOT contract doesn't guarantee the road will ever be built. It also states that money or property contributed by local governments won't be returned if the project is canceled. County Mayor Ed Mitchell said that finishing the extension has been one of his campaign priorities since he first ran in 2010.
The schedule itself has moved. TDOT's April 2024 reevaluation listed right-of-way acquisition as funded in Fiscal Year 2032. TDOT's current project page says Fiscal Year 2026. Land acquisition has moved up roughly six years, while the construction estimate hasn't changed.
| Milestone | Date |
|---|---|
| Record of Decision signed | August 31, 2017 |
| Conceptual Stage Relocation Plan | February 3, 2023 |
| FHWA reevaluation, right-of-way listed for FY2032 | April 2024 |
| TDOT transmits local agreement | May 1, 2026 |
| Blount County approves $5 million | July 16, 2026 |
| First county payment | June 2027 |
| Estimated construction start | Fiscal Year 2036 |
| Estimated completion | To be determined |
As of early October 2026, we haven't found reporting that confirms a signed agreement, appraisals, owner notices, or parcel purchases. The copy of the agreement attached to the county record still has blank date and signature fields. Acquisition is funded and authorized. Whether it has actually started is something to confirm with TDOT, not assume.
Where the Line Runs
TDOT describes the extension as a 4.38-mile, four-lane divided highway from SR 33 to US 321/SR 73. Interchanges are planned at SR 33, US 411/Sevierville Road, and US 321, and every other road crossing would pass over or under the highway without access. Heading south, the alignment in the environmental documents:
- Starts east of SR 33 and passes through the Pellissippi Place Research and Technology Park area
- Crosses Wildwood Road and Brown School Road
- Crosses US 411/Sevierville Road east of its Davis Ford Road intersection, then crosses Davis Ford Road
- Ends at US 321/SR 73 just east of Flag Branch
At the southern end, TDOT picked a western alignment shift in July 2013. The shift avoided a sensitive part of an archaeological site that is eligible for the National Register. That decision shows a principle that holds throughout the project: the line can still move. TDOT says plainly that it can't know how any particular property will be affected until final design plans and field surveys set the right-of-way limits. The relocation counts above are planning estimates. They aren't a list of addresses.
Noise is the other effect to know about. TDOT's December 2023 noise study found traffic noise impacts at 66 residential and recreational properties. The earlier study had found 103, and TDOT has identified one noise barrier as likely to be built.
If TDOT Eventually Knocks
Owners whose property ends up in the final right-of-way go through a set process. According to TDOT's acquisition brochure, updated April 30, 2026, licensed appraisers inspect the property and review public records and recent nearby sales to estimate fair market value. When TDOT takes only part of a parcel, the appraisal also accounts for the effect on the remaining land. A TDOT acquisition agent then explains the project and presents an approved written offer. Payment usually arrives within 60 days of an agreement and ordinarily before the owner has to move out.
TDOT's residential relocation brochure, updated July 2026, says displaced occupants may receive moving assistance. They can choose reimbursement of actual reasonable costs or a fixed payment based on the number of rooms. Eligible occupants may also qualify for replacement-housing supplements, depending on how long they've lived there and whether they own or rent. Displaced occupants get at least 90 days to relocate after the state takes possession of the home.
That process protects owners, but it runs on TDOT's schedule. Buyers who close on a house in the corridor this year accept that schedule as part of the purchase.
Checking a House Before You Offer
For any home east or southeast of Maryville between SR 33 and US 321, these steps cost nothing and can happen before an offer:
- Open the TDOT project page and compare the property's location with the two updated project display maps from September 2022. Their legend shows proposed right-of-way, property lines, and temporary construction and slope easements.
- Review the 2024 right-of-way field review plans listed with the reevaluation documents.
- Ask the seller in writing whether they've been contacted by TDOT or a TDOT appraiser about the extension. Don't rely on the roads question on the disclosure form to bring it up.
- Keep in mind that every map labeled preliminary can still change, and plan your inspection and due diligence period with that in mind.
None of this is legal advice. For specific questions about a parcel or a contract, talk with a real estate attorney and contact TDOT directly.
FAQ
Is the extension definitely going to be built? Nothing guarantees it. The TDOT agreement doesn't promise construction, and TDOT lists the completion date as to be determined.
Has TDOT started buying homes? As of early October 2026, we haven't seen confirmation of appraisals, owner notices, or purchases. Funding has been approved, but the paperwork in the county record wasn't yet signed.
Does a house near the corridor have to be disclosed as such? The RF201 form doesn't ask about proximity to a proposed highway. It asks about authorized road changes affecting the property or land next to it, and Tennessee law doesn't require sellers to investigate.
If you're weighing a home anywhere near the Pellissippi corridor, Tilley Home Group can walk you through TDOT's maps parcel by parcel and help you write the right questions into your offer. If you already own near the line, start with a free home valuation so you know where your property stands before TDOT's appraisers ever arrive.