Four roads meet at the south end of Carpenters Grade Road in Maryville: Carpenters Grade, Cochran, Raulston and Peterson. The Marathon station sits on the corner. For years that crossing has run on four stop signs. Brian Boone, Maryville's director of Engineering and Public Works, told WBIR the intersection "has outgrown its four stop signs."
On Wednesday, Oct. 21, 2026, traffic moved in both directions on Carpenters Grade again for the first time since the final construction phase began. The city called the reopening "a major milestone." The pieces that set this corridor's design from the start were a signal at that four-way intersection and a multi-use path for people walking and biking. Both are part of the closing stretch of work, and the contract runs until Jan. 14, 2027.
Why the Intersection Drove the Whole Project
The city says the corridor carries more than 11,000 vehicles a day. Kevin Stoltenberg, the city engineer, gave the same number when the project was first presented to residents in November 2019. At that meeting he told The Daily Times, "We're at 11,000 vehicles a day right now, and the road itself is starting to crumble."
That 2019 coverage also explains why the four-way stop got so much attention. Stoltenberg said city consultants projected that the intersection would fail by 2040 if nothing changed, and that traffic studies showed congestion getting worse as development continued in that part of town. The project as a whole covers roughly 4,500 feet, from the Raulston/Peterson/Carpenters intersection to Cochran Road. The city's plan calls for a new traffic signal at the intersection by the end of the project, meant to improve safety and traffic flow on Cochran, Raulston, Peterson and Carpenters Grade.
Boone told WBIR how he sees the change over time:
"Time changes everything. You can go back 20 years, and a two-way, stop-controlled intersection with not a lot of traffic, no big deal."
In the same report he described the broader goal as bringing narrower roads that the city has annexed up "to a more urban standard, that works for both cars, trucks, walkers, joggers and bicycles."
The 2019 Pitch Compared With the Road Being Finished Now
The project's basic shape held from the first public meeting to construction. The budget and the calendar did not.
| Presented to residents, Nov. 2019 | As built, 2025–2026 | |
|---|---|---|
| Estimated cost | $2.8 million, split 80/20 between TDOT and the city | $9 million, with $7.5 million from state and federal sources and the rest from Maryville |
| Expected finish | Possibly spring 2024 | Year-end 2026 target, contract date Jan. 14, 2027 |
| Lanes | Two 9-foot lanes widened to 11 feet | Lanes widened for two-way traffic |
| Intersection | A possible signal at Raulston/Peterson/Carpenters Grade | A signal planned for Cochran/Raulston/Peterson/Carpenters Grade |
| Walking and biking | A new multi-use walkway | A multi-use path, still under construction |
The slower pace came from the steps involved in using state money. Stoltenberg said in 2019 that the city had considered fixing the road on its own but chose state funding, which meant an environmental study. The city's project timeline shows how long those steps took. TDOT authorized final design in September 2020 and right-of-way acquisition in June 2021. It authorized construction on Sept. 19, 2024. Cleary Construction won the bid that winter, and work began March 17, 2025. The widening had first appeared in the Knoxville Regional Long Range Mobility Plan in 2009, with a horizon year of 2024. Stoltenberg had also warned residents early on: "What gets built is almost never what you see on the front end of the design."
How the Path Carried Cars Before It Carried Anyone on Foot
During Phase III, the path served as part of the road. The city's Phase III traffic plan sent northbound Carpenters Grade traffic onto a detour along Cochran Road. Southbound traffic stayed on Carpenters Grade and ran on the multi-use path between Melrose Station and Barrington.
Neighborhood exits changed under the same plan. Drivers leaving Cross Creek, Oxford Hills and Knightsbridge were limited to right turns onto Carpenters Grade. Drivers leaving the Villas at Carpenters Grade, Legacy Court and Kirkland Estates were limited to left turns. A temporary traffic signal at Carpenters Grade and Cross Creek Drive helped subdivision traffic get onto the road. The city's plan says that signal comes down once two-way traffic returns as the project nears completion.
The earlier phases were the less visible work. Phase I relocated utilities, moved Cochran Road to a new alignment where it meets Raulston Road, and added new curbing. Phase II continued the curb and utility work, took down the old electrical poles, and paved Raulston Road with asphalt. As of the city's June 1, 2026 update, the new water and sewer lines were fully installed, and the road reconstruction had been 60% complete as of April. The same update expected two-way traffic in late September. It came on Oct. 21.
What the Oct. 21 Reopening Left Unfinished
The road now handles traffic both ways. The city's Oct. 21 notice says crews will keep working on "remaining roadway and multi-use path improvements," sometimes with flaggers around crews or equipment. The project page's most recent status log covers the week of Oct. 12, the week before the reopening. That week, crews installed new curb and gutter along parts of the road, sealed connections inside storm drainage structures, and placed new asphalt on sections of Carpenters Grade, including near the Ludlow Drive intersection to smooth the change between road surfaces.
The city ties three pieces of work to the end of the project:
- The multi-use path. In the Oct. 12 week, crews were leveling and shaping it to get ready for the stone base and the other path materials. The Oct. 21 notice lists path work as continuing.
- Final paving on relocated Cochran Road. The city's FAQ says the rough surface on the relocated section will be smooth after final paving near the end of the project.
- The four-way signal. The city plans to install it at Cochran, Raulston, Peterson and Carpenters Grade by the end of the project.
The city's target is still the end of 2026. The contract completion date is Jan. 14, 2027, and the city says it is optimistic the project will finish before that date. In its report heading into 2026, The Daily Times noted that officials had cautioned the schedule could shift with outside factors.
Keeping Up Between Now and January
The City of Maryville project page is the main source for updates. The city says it posts them every two weeks. Road notices for the whole city, including lane closures, appear on the city's News, Traffic & Service Updates feed.
For a problem tied to your own property, such as a driveway, a drainage question or a work crew, Cleary Construction runs a resident hotline at 1-800-972-1823. Give project number 24411 when you call. The city says live people answer the line 24 hours a day, every call is logged, and the company guarantees a call back. For questions about the project itself, the city's Engineering and Public Works Department is at 865-273-3500.
The city has also asked property owners along the corridor to leave the survey stakes and colored utility flags in place when mowing or trimming. The stakes show property lines, drainage easements, slope limits and driveway locations, and contractors rely on them through the end of construction.
If you own a home on or near Carpenters Grade and want to know how a finished corridor with a path and a signalized intersection could factor into your home's value, Tilley Home Group can walk you through it. Start with a free home valuation, and we'll keep watching this project's progress with you through January.